To: Colleagues interested in the Burrowes renovation project
From: Chris Hort
Please see the photos and associated project update summary below. I think the mall area surrounding Burrowes building was dressed up nicely for commencement this weekend and we received a lot of positive feedback about the project. The overall schedule remains on track and it'll be a busy summer with all the utility work across the mall area starting shortly.
If you have any project specific questions, please let me know. Thanks, Chris
Overall Progress:
-
South Wing 4th & 3rd floor demolition & abatement complete
-
Core Building 3rd floor abatement & demolition complete
-
Window removal has begun on the top floor
-
South Wing 2nd floor demolition complete and abatement in progress
-
Core Building 2nd floor abatement complete and demolition is in progress
-
North Knuckle demolition is in progress
-
Basement excavation is in progress
Upcoming Work:
-
Abatement and demolition will continue down thru the building
-
Shoring added to basement for new foundation work
-
MEP hanger rough-in starting on upper floors
-
Site utility work will start in the Pattee Mall area